Silver Lake Boat Launch and Site Improvements – Construction Update

September 25, 2020

Construction this week included installation of the remaining stormwater components, site fine grading, and staining the large block retaining wall. Following installation of the storm area drains and pipe, fine grading behind the retaining wall was performed in preparation for seeding and installation of a safety fence on the top portion of the retaining wall. Staining of the retaining wall is anticipated to occur on Friday, September 25th. Over the next two weeks the focus will be on installation of the new lift station, completion of the boat launch, and grading and paving the new access drive. Currently, the contractor is on schedule to be substantially complete the week of October 12th.